How Long Does a Hydrogeological Study Take?

The published minimums and notice periods that set the schedule, and how to keep them off the critical path.

How long a hydrogeological study takes depends far less on writing the report than on three clocks the consultant does not control: how long the reviewer wants groundwater monitored, how long the field tests have to run, and how far ahead approvals and notices have to be in place. No agency publishes a standard duration for a whole study, but most of those clocks are written down, and they are set out below with their sources.

The longest clock: monitoring

For any study that has to establish the seasonal high water table, the monitoring period is the critical path. Published minimums vary widely:

WhoMonitoring expected
Lake Simcoe Region Conservation Authority (LSRCA)Generally at least 12 continuous months to support a planning application, including the seasonal high
York Region terms of referenceFour-season monitoring, including seasonally and historically high levels
Hamilton (City urban hydrogeological study guidelines)Three months of biweekly readings for mid- and high-rise sites, longer where highly porous deposits are found; two years of continuous logging for low-rise subdivisions before detailed design
Mississauga (terms of reference)At least three monthly measurements over at least three months
Brampton (terms of reference)At least three months of water level monitoring

The same project can therefore need three months in one municipality and a year in the next. The local terms of reference decide it, so read them before the wells go in.

Tests with fixed lengths

  • Private well test for a severance. Guideline D-5-5 calls for at least six hours of continuous pumping, then recovery monitoring until 95% recovery or 24 hours, whichever is less, followed by laboratory analysis of the samples.
  • Pumping tests registered on the EASR. Under water taking EASR regulation (O. Reg. 63/16), a pumping test can be registered rather than permitted when it takes more than 50,000 and not more than 5,000,000 litres a day over seven or fewer days within a 30-day period.
  • Hydraulic response tests. Single-well tests in monitoring wells take hours, not days, but they need wells that are installed, developed and stable first.

Approvals and notices to book ahead

StepPublished notice or review time
EASR dewatering: notice before pumpingWritten notice to affected water users and the ministry district office at least 48 hours before the first taking (water taking EASR regulation (O. Reg. 63/16))
Toronto sewer dischargeApplications at least eight to 12 weeks before discharge (City of Toronto)
York Region discharge, primary municipalitiesUp to six weeks to review a complete package (York Region)
Permit to Take WaterMinimum 30-day Environmental Registry comment period where posting is required; no fixed review time (MECP guidance on permits to take water)
Permit to Take Water renewalApply six months before the expiry date (MECP guidance on operating your permit)

For a construction project these run in parallel with the study, not after it. The step-by-step guide to dewatering under the EASR shows where each falls.

How long a finished study stays usable

Timing matters at the other end too. Innisfil's terms of reference treat a study as valid for up to 18 months from its date, unless site conditions change or development has started; after that, monitoring data may have to be reassessed. A study finished long before the application is filed can cost a second round of work, so time the report to the application. Our Innisfil page covers that rule.

Keeping the study off the critical path

  1. Read the terms of reference first. The monitoring minimum is the single biggest factor, and it is known before any drilling.
  2. Install wells with the geotechnical drilling. One mobilization, and the monitoring clock starts as early as possible. See hydrogeological study vs geotechnical report.
  3. Catch the spring. Wells installed in late winter capture the seasonal high in the first months of monitoring; wells installed in summer may have to wait most of a year for it.
  4. Start permits in parallel. Sewer discharge applications and, where needed, a Permit to Take Water have their own notice and review times; they can begin once the dewatering estimate is reliable.
  5. Answer review comments with data, not argument. A resubmission that adds the missing readings or tests moves faster than one that explains why they were not needed.

For Toronto sites, where construction dewatering and sewer discharge approvals usually run together, the local page sets out the City's rules. The development hydrogeological study page covers scope and cost.

Related questions

Can a hydrogeological study be done in a few weeks?

Some can: work that relies on existing information, such as a water balance built from soils, land cover and climate data, is mostly desk work. A study that needs new monitoring wells and a seasonal record cannot be shortened below the monitoring period the reviewer expects, however quickly the report is written.

Why do reviewers care so much about spring water levels?

Because the seasonal high, usually in spring, decides basement and foundation design, how deep infiltration features can go and how much dewatering a project needs. A record that misses the spring has to estimate it, and reviewers look hard at that estimate.

Does the ministry publish a review time for a Permit to Take Water?

No: the ministry's permit guidance describes the steps, including a minimum 30-day comment period on the Environmental Registry where posting is required, but there is no fixed decision time. Plan the field work and application well ahead of when water is needed.